The City of Pickering says installation of interior metal flashing around the existing skylights at Chestnut Hill Developments Recreation Complex is scheduled from Monday, September 28, to Friday, October 2.
The work is divided into phases: September 28 and 29, September 30, then October 1 and 2. Areas directly below the work will be closed for safety while the work is underway.
The health club will be closed to members on October 1 and is scheduled to reopen at 7 p.m. on October 2.