Scugog Line 2 closes Oct 26 for two-week culvert replacement

Prefabricated steel modular bridge goes in 1.35 km east of Hwy 7/12; closure runs from Old Simcoe Road to Diamond Side Road.

Stacked concrete culvert pipes outdoors under a clear blue sky; no people visible
Stacked concrete culverts. Scugog is replacing the Line 2 culvert east of Highway 7/12 with a prefabricated steel modular bridge the week of October 26. · Credit: MNRD JON, Pexels

The Township of Scugog has contracted Northern Mat & Bridge to replace the Scugog Line 2 culvert, about 1.35 kilometres east of Highway 7/12, with a prefabricated steel modular bridge the week of October 26.

The installation is expected to take about two weeks, weather permitting, including paving of the bridge approaches. The township says the prefabricated design allows for a lower price tag and quicker installation.

The contractor mobilizes October 23, and a road closure will be in effect from Old Simcoe Road to Diamond Side Road starting at 8:00 a.m. on October 26. Local traffic will be maintained, but through traffic will not be permitted through the construction zone.

Behind the story

Sources & publication details

Byline
Daily Durham News
Published
Oct 20, 2026, 6:13 p.m.
Source
www.scugog.ca

The Durham brief

A little closer to home.

Local stories worth knowing, straight to your inbox.