Clarington: OEB orders renewed Darlington SMR settlement talks after delay disclosure

The Ontario Energy Board has ordered settlement talks to resume December 8 after OPG disclosed the first Darlington small modular reactor will miss its October 2030 in-service date. OPG must report back by December 11.

The Darlington Nuclear Generating Station in Clarington, seen from Lake Ontario, with its reactor containment dome. File photo.
File photo: the Darlington Nuclear Generating Station in Clarington. (Photo: Óðinn / Wikimedia Commons, CC BY-SA 2.5 CA) · Credit: Óðinn / Wikimedia Commons, CC BY-SA 2.5 CA

The Ontario Energy Board has ordered Ontario Power Generation and DNNP LP back to settlement talks over payment amounts for the Darlington small modular reactor project, after the applicants disclosed the first reactor unit will not meet its forecast October 2030 in-service date. In Procedural Order No. 10, dated Monday, November 16, 2026, the board directed the settlement conference to continue on Tuesday, December 8, 2026, and ordered the applicants to report on the status of the talks by Friday, December 11, 2026.

Source: www.rds.oeb.ca

OPG and DNNP LP had filed a settlement proposal on October 5, 2026, covering payment amounts for January 1, 2027 to December 31, 2031. On November 10, the applicants told the board the first small modular reactor unit and the common-scope facilities under construction are no longer expected to achieve the October 2030 in-service date, and filed an Impact Statement removing certain requested approvals related to the reactor unit and the common-scope facilities. The intervenors who signed the settlement proposal agreed on November 12 to return to the settlement conference.

Engineering News-Record reports the November 10 filing cut the proposed revenue requirement by about $1.6 billion over five years, from $1.9 billion to $280 million, and removed forecast generation of 0.5 terawatt-hours in 2030 and 1.9 terawatt-hours in 2031. OPG expects its revised cost and schedule assessment to be substantially complete by mid-2027, while construction continues at the Darlington site.

Behind the story

Sources & publication details

Byline
Daily Durham News
Published
Nov 18, 2026, 8:57 a.m.
Source
www.rds.oeb.ca

The Durham brief

A little closer to home.

Local stories worth knowing, straight to your inbox.